Civil enginneering

Reconstruction of the Greenway Footbridge over the Osor Stream between Anglès and La Cellera de Ter

Demolition of the old railway bridge, collapsed by Storm Gloria, and construction of a new footbridge.

In January 2020, Storm Gloria damaged the old railway bridge over the Osor stream. The bridge’s structure was undermined, causing some of its piers to collapse. As an emergency measure, a new footbridge was built with a single-span metal structure, designed to withstand a 500-year flood return period. The new metal lattice footbridge has a length of 50 meters and a width of 2.50 meters for pedestrians and cyclists.

Features

Total length of the footbridge: 51.00 m
Clear passage width: 2.50 m
Free hydraulic section: 220 m² (48% improvement)
Construction budget: €410,476.67 (excluding VAT)

Client: Consorci Vies Verdes de Girona
Year: 2020
Riera d’Osor (Anglès i la Cellera de Ter)

Other projects
Subscribe now
Receive the latest news from ABM by email. Find out about the latest projects we have worked on.


  • ABM SERVEIS D'ENGINYERIA I CONSULTING, S.L., as data controller, will process your data in order to send you our newsletter with commercial news about our services. You can access, rectify and delete your data, as well as exercise other rights by consulting the additional and detailed information on data protection in our Privacy Policy
Subscribe now
Receive the latest news from ABM by email. Find out about the latest projects we have worked on.


  • ABM SERVEIS D'ENGINYERIA I CONSULTING, S.L., as data controller, will process your data in order to send you our newsletter with commercial news about our services. You can access, rectify and delete your data, as well as exercise other rights by consulting the additional and detailed information on data protection in our Privacy Policy
×ATENCIÓ: Cookies no configurades en l'idioma actual. Revisa la teva configuració al plugin, gràcies!